February 18, 2009

 

All,

News of Today (based on Email from Olaf and calls with Olaf and Doug)

Things are moving to and at Lake E, supported by good weather (no wind, few clouds, -40C):

- Meanwhile, 9 containers have made it to lake, more are expected to arrive soon.

- The 8 sledges that finally will form the basis for the drilling platform have been pulled out of the containers; so, construction work has started.

- One of the now empty containers was used to store the liners; they look good, none (!) of them became broken.

- The frostfighters of DOSECC have been tested; they work properly so far.

- Also the heatable container for core storage was tested and runs fine.

- It is planned that the core storage container and the laboratory container will be positioned in a way that allows for short transport between core logging and final storage.  

- An inspection of the D1 pad showed significant progress in freezing, however, as expected, another day is needed to freeze the water completely that has been spilled yesterday.

Let´s hope that weather in the next days keep calm, thus allowing for comparable progress at Lake E 

 

Cheers for now

Martin

©  Elgygytgyn Drilling Project
Technische(r) Ansprechpartner(in):

Dise Seiten werden nicht mehr gepflegt und werden lediglich als Archiv vorgehalten


Andreas Vogt
geändert: 13. August 2015
erstellt: 30. Juni 2011