January 27, 2009

 

All,

news as of today (based on emails and call with Olaf):

 

- The pumps that have arrived with the helicopter were checked - everything is complete, they are working properly and are of high quality

 - Volker Neth has formulated "procedures for working on the ice", which were forwarded to Gutov

 - Gutov´s crew has pulled one of the baloks to site D1, which will function as shelter for the ice strengthening work out there

- Tomorrow, the bulldozer will be checked and, if everything is okay, will for the first time travel to D1 to start snow clearing

 - Little wind, -30 degreed C

 - Everybody is fine

 

Cheers for now

Martin

 